Singapore now 1GW away from meeting target of importing 4GW of low-carbon electricity by 2035.
Company | Import Capacity |
Pacific Medco Solar Pte Ltd, formed by PacificLight Renewables Pte Ltd, Medco Power Global Pte Ltd and Gallant Venture Ltd | 0.6GW |
Adaro Solar International Pte Ltd., formed by PT Adaro Clean Energy Indonesia | 0.4GW |
EDP Renewables APAC | 0.4GW |
Vanda RE Pte Ltd, formed by Gurin Energy Pte Ltd and Gentari International Renewables Pte Ltd | 0.3GW |
Keppel Energy Pte Ltd | 0.3GW |